    TCN ENERGIZES NEW 150MVA TRANSFORMER IN DELTA IV SUBSTATION, UGEHELLI

    Published on

    By Abdul lawal

    The Transmission Company of Nigeria (TCN) has successfully installed and energized a new 150MVA 330/132/33kV Interbus Transformer (IBTR) at Delta IV Transmission Substation, Ughelli, Delta State at about 13:09Hrs on Sunday 16th October, 2022 and loaded at 15:19Hrs on Monday, 17th October 2022.

    Statement issued by TCN General Manager,Public Affairs, Ndidi Mbah said commissioning into service of the new 150MVA power transformer has restored the capacity of the substation by 132MW.
    Consequently, TCN is now able to evacuate/wheel more power for Benin Electricity Distribution Company (BEDC) to offtake from the substation for onward delivery to electricity consumers in Ughelli, Warri, and its environs.

    According to her the installation of the new 150MVA Interbus Transformer has restored flexibility to the substation by enabling TCN to evacuate power from Transcorp Power Limited at both at 330kV and 132kV voltage levels. This means an increase in bulk power transmitted through the substation and improved grid stability.

    “TCN assures Nigerians of her avowed commitment to enhancing bulk power delivery and grid reliability and pledges that it would continue to execute projects geared towards entrenching a robust transmission grid as catalogued in its Nigerian Electricity Grid Maintenance Expansion and Rehabilitation Programme” the statement ended

    Latest articles

    Niger: Bandits kill six in Tungan-Makeri, burn police station in Konkoso

    Armed bandits have allegedly killed six persons in Tungan-Makeri and set a police station...

    2027: Reps to hold emergency sitting

    The House of Representatives has scheduled an emergency sitting for Tuesday, February 17, 2026,...

    2027 Nigerian General Elections Timetable Released by INEC

      - Political Parties Primaries: Conducted between July 1 and September 30, 2026. - Submission of...

    THE UNIVERSITY AS A CATALYST FOR SOCIETAL DEVELOPMENT (PART 7)

      INTRODUCTION In our last episode, we examined the core functions of Universities as tools for...

    More like this

    Niger: Bandits kill six in Tungan-Makeri, burn police station in Konkoso

    Armed bandits have allegedly killed six persons in Tungan-Makeri and set a police station...

    2027: Reps to hold emergency sitting

    The House of Representatives has scheduled an emergency sitting for Tuesday, February 17, 2026,...

    2027 Nigerian General Elections Timetable Released by INEC

      - Political Parties Primaries: Conducted between July 1 and September 30, 2026. - Submission of...