More
    HomemetroBlackout looms in Lagos as TCN begins 25-day maintenance on Monday

    Blackout looms in Lagos as TCN begins 25-day maintenance on Monday

    Published on

    Electricity users in Lagos will experience ‘intermittent’ blackout as the Transmission Company of Nigeria (TCN) begins a 25-day maintenance of the Omotosho – Ikeja West 330kV power line.

    The TCN in a statement said the Nigerian Electricity Regulatory Commission (NERC) and the National Independent System Operator (NISO) have approved the “critical infrastructure upgrade”.

    “The upgrade involves the installation of Optical Ground Wire (OPGW) fibre cable on the Omotosho/Ikeja West 330kV transmission line, scheduled from July 28, 2025, to August 21, 2025 from 8 am to 5 pm,” the TCN said in a statement by its General Manager (GM), Public Affairs, Ndidi Mbah.

    During the period, the agency said, “power will be restored through the line after each day’s work, all other circuits will remain operational to ensure a stable power supply to the Lagos complex during the exercise”.

    It said the upgrade will “enable full operationalization of the Supervisory Control and Data Acquisition (SCADA) system” and enhance the real-time monitoring and management of the power grid.

    Meanwhile, electricity distribution companies in Lagos State – the Eko Electricity Distribution Company (EKEDC) and the Ikeja Electricity Distribution Company (Ikeja Electric) have informed customers about the planned upgrade.

    In separate public notices, both DISCOS said there will be “intermittent power supply” during the period.

    “Dear Esteemed Customer,” Ikeja Electric said. Please be informed that the Transmission Company of Nigeria (TCN) will carry out scheduled maintenance on the Omotosho-Ikeja West 330kV transmission line from Monday, July 28, to Thursday, August 21, 2025, between the hours of 8:00 AM and 5:00 PM daily.

    “During this period, customers may experience intermittent power supply and load shedding across our network due to the planned TCN outage,” the DISCO said.

    On its part, EKEDC wrote: “Dear Valued Customer, Kindly be informed that there will be a planned outage by our partner, Transmission Company of Nigeria (TCN). Date: Monday, 28th July to Thursday, 21st August, 2025. Time: 08:00 – 17:00 hrs (daily); Reason: To enable works to be safely carried out on the Omotosho – Ikeja West 330kV power line; Impact: Intermittent outage and load shedding across our network. Affected Areas: Across our network coverage.”

    Latest articles

    NANS Raises Alarm Over Attacks On Nigerians In South Africa

    The National Association of Nigerian Students (NANs) has called on the Federal Government to...

    18th convocation: DELSU seeks partnership to maintain academic excellence

    The Delta State University (DELSU), Abraka, has appealed to Nigerians, for support to enable...

    2025 budget: questions raised over reported 7% allocation for security equipment

    Amid the escalating security crisis across Nigeria, recent records from the Federal Government’s Open...

    The IBADAN DECLARATION by Nigeria’s leading opposition politicians…

    By Bola BOLAWOLE The country’s leading opposition political parties descended, last week Saturday, on the...

    More like this

    NANS Raises Alarm Over Attacks On Nigerians In South Africa

    The National Association of Nigerian Students (NANs) has called on the Federal Government to...

    18th convocation: DELSU seeks partnership to maintain academic excellence

    The Delta State University (DELSU), Abraka, has appealed to Nigerians, for support to enable...

    2025 budget: questions raised over reported 7% allocation for security equipment

    Amid the escalating security crisis across Nigeria, recent records from the Federal Government’s Open...